Title: Change Order to Contract No. 15EJ-171, 34.5 KV Cable Replacement M-Line MVS Switching Station and MTF, MSS, MPS, and MTW Substations, for Additional Expansion Joints and Phenolic Reinforced Thermosetting Resin Conduit (C.O. No. 007). Board requested to authorize.