Change Order to Contract No. 05HA-100, El Cerrito Del Norte Station Modernization Project, with Clark Construction Group, LLC.
i. Upgrade the Planned 10KW UPS to 40KVA (C.O. No. 33).
ii. Revise Overhead Power and Communication Conduits and Layout
(C.O. No. 39).
iii. Procure Additional Fire Alarms Devices, from 73 to 229
(C.O. No. 54).
iv. 5 Month Delay Compensation (C.O. No. 55).
v. Accelerate Phase 1 of Water Intrusion Mitigation Project
(C.O. No. 82).
vi. Retrofit Two Accessible Fare Gates (C.O. No. 90).
vii. Construct a New PG&E Service Meter for New Fire Pump
(C.O. No. 91).
Board requested to authorize.