Title: Change Orders to Contract No. 09DJ-150A, TBT Cathodic Protection Reference Cell Replacement, with DMZ Builders. a. Complete the Contract Work during Weekends and Extension of Time (C.O. No. 9.1 and 16). b. Developing a Preliminary Welding Plan (C.O. No. 10). c. Removal of the Two Newly Installed Panels and Pin Brazing Conduits (C.O. No. 11 and 12). d. Conduit and Cables Quantity Overrun (C.O. No. 13 and 15). e. Provide Roadway Worker Certified (RWP) Labor (C.O. No. 14). Board requested to authorize.
Attachments: 1. Change Orders to Contract No. 09DJ-150A, TBT Cathodic Protection Reference Cell Replacement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Change Orders to Contract No. 09DJ-150A, TBT Cathodic Protection                     

Reference Cell Replacement, with DMZ Builders.

a.          Complete the Contract Work during Weekends and

Extension of Time (C.O. No. 9.1 and 16).

b.                     Developing a Preliminary Welding Plan (C.O. No. 10).

c.                     Removal of the Two Newly Installed Panels and Pin Brazing

Conduits (C.O. No. 11 and 12).

d.                     Conduit and Cables Quantity Overrun (C.O. No. 13 and 15).

e.                     Provide Roadway Worker Certified (RWP) Labor (C.O. No. 14).

Board requested to authorize.