Title: Change Order to Contract No. 15IF-140, Powell Street Station Modernization Project, with Proven Management, Inc., for Global Settlement of Delay Costs, Pending Notices of Potential Claims, and Protested Change Notices and Change Orders. Board requested to authorize.
Attachments: 1. Change Order to Contract No. 15IF-140 - EDD
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Change Order to Contract No. 15IF-140, Powell Street Station Modernization Project, with Proven Management, Inc., for Global Settlement of Delay Costs, Pending Notices of Potential Claims, and Protested Change Notices and Change Orders.