Title: Change Orders to Contract No. 15EK-140, Traction Power Substation Replacement ASL Installation, with Aldridge Electric, Inc. Board requested to authorize. i. Reinforced Thermosetting Resin Conduit Upsizing 4” to 5” Labor and Materials (C.O. No. 004). ii. 5” Reinforced Thermosetting Resin Conduit Hanger Modifications - Resubmittals Inefficiencies and Extended Overhead (C.O. No. 010B).
Attachments: 1. Change Orders to Contract No. 15EK-140, Traction Power Substation Replacement - EDD
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Change Orders to Contract No. 15EK-140, Traction Power Substation Replacement ASL Installation, with Aldridge Electric, Inc. 

Board requested to authorize.

 

i.                     Reinforced Thermosetting Resin Conduit Upsizing 4” to 5” Labor and Materials (C.O. No. 004).

ii.                     5” Reinforced Thermosetting Resin Conduit Hanger Modifications - Resubmittals Inefficiencies and Extended Overhead (C.O. No. 010B).